TAMRMS#: B05
5.9
title
RECR-050, RWP Meadowview Construction
Notice given by: Councillor Hughes
label
BUDGET POSTPONED MOTION:
recommendation
That the RECR-050, RWP Meadowview Construction is amended to only include the utilities and parking lot portion, that the charter costs are amended accordingly and that the remainder of the project charter is considered a separate charter for future years considerations.
body
Administration’s Understanding of the Intent of the Motion:
Administration will adjust the 2027 RECR-050 RWP Meadowview Construction charter to reduce the project scope by removing the interpretive signage and washroom facilities, the estimated resulting cost is provided in the attachment 1- Confidential PM-27-021.
SUMMARY
This report provides background on the charter strategy for completing the Red Willow Park West Master Plan and discusses impacts related to the alternative strategy proposed in the above postponed motion.
ALIGNMENT TO COUNCIL DIRECTION OR MANDATORY STATUTORY PROVISION
N/A
BACKGROUND AND DISCUSSION
In alignment with the Red Willow Park West Master Plan, capital work was split into three phases:
/
The scope of work proposed for Phase 3 reflects the work required to complete the vision and intent of the Red Willow Park West Master Plan and, more specifically, the role of White Spruce Park as an educational destination and key access point to both the existing Red Willow trail system and planned expansions into Lakeview Business District.
Phase 3 key features include:
/
Should this motion be approved, it would limit the overall service provision for both White Spruce Park and Red Willow Park West. It is also anticipated that any immediate cost savings from additional project phasing would have future cost implication related to:
Cost escalation between phases;
Additional engineering, tendering, contract administration, and project management costs;
Additional contractor mobilization and demobilization costs...