File #: AR-25-231    Version: 1 Name:
Type: Agenda Reports Status: Agenda Ready
File created: 5/1/2025 In control: Standing Committee of the Whole
On agenda: 6/10/2025 Final action:
Title: Northeast Servicing Update Presented by: Jordan Betteridge, Manager Asset Management, Land, Integrated Infrastructure Service, Engineering Services
Attachments: 1. Att1 - Pipe Storage Location, 2. Att2 - Schematic Overview
TAMRMS#: B06
5.2


Information Item Only

title
Northeast Servicing Update
Presented by: Jordan Betteridge, Manager Asset Management, Land, Integrated Infrastructure Service, Engineering Services

body
SUMMARY

This report provides an update regarding a developer submitted proposal to utilize existing deep sanitary trunks for pipe storage, which would create additional interim capacity in the sanitary system allowing additional stages of development to occur in the Jensen Lakes and Erin Ridge North areas until the ultimate Northeast Servicing Project is commissioned. An update to the ultimate Northeast Servicing Project funding will be provided through a recommended in-camera component to provide confidential information and progress regarding Administration's work with third parties on a substantive funding model for the ultimate Northeast Servicing Project.

ALIGNMENT TO COUNCIL DIRECTION OR MANDATORY STATUTORY PROVISION

N/A

BACKGROUND AND DISCUSSION
Development within the northeast part of the City (e.g. Jensen Lakes and Erin Ridge North) is expected to utilize all of the existing sanitary capacity for the area. To address the long-term servicing needs for these development areas, the City has been working towards the ultimate Northeast Servicing Project which would entail construction of new utility infrastructure which would create additional capacity in the system that is needed to support the long-term growth in the North and Northeast. In advance of this ultimate Northeast Servicing Project, the developers have requested the City evaluate an interim solution that could provide limited additional sanitary capacity to support additional stages of development in the near term.
Interim Pipe Storage Concept:

In late 2024, two developers submitted proposals for the City to consider an interim sanitary solution. The proposed approach utilizes an existing deep sanitary trunk system to temporarily store peak sanitary and wet weather flows during wet weathe...

Click here for full text