REQUEST FOR DECISION


title
Founders Walk Phase III, Children's Bridge Lighting
Presented by: Adam Turnbull, Cultural Facilities & Resources Manager, Community Services

label
RECOMMENDED MOTION(S)
recommendation

That the budget for capital project 424317, Founders Walk Phase III (CULTR-005) be increased from $108,000 to $210,000 to be funded from the Capital Reserve.

body

SUMMARY

Administration is requesting additional funding to cover a required change in project scope. This change is needed to ensure the Children's Bridge has power available to operate the planned LED colour-changing lighting, which is part of CULTR-005: Founders Walk Phase III - Children's Bridge.

ALIGNMENT TO COUNCIL DIRECTION OR MANDATORY STATUTORY PROVISION

N/A.

BACKGROUND AND DISCUSSION

In 2023 Council approved $108,000 for Founders Walk Phase III, project 424317, to be funded from the 2024 Capital Budget. The project scope was to provide colour-changing LED lighting for the Children's Bridge.

The original scope of the project did not include providing power to the bridge. Instead, Administration planned the work to align with the anticipated Millennium Park construction for greater efficiency. However, with the Millennium Park growth charter now rescinded, additional funding is required to supply power to the bridge. (Attachment: CULTR-005 Founders Walk Phase 3 Capital Charter)

Administration is seeking Council approval for the extra budget, as it exceeds the CAO's delegated authority.

Approved by Council in 2023:
Additional Budget required for Power to Bridge:
Total:
$108,000.00
$102,000.00
$210,000.00

The Children's Bridge lighting construction will get underway later in 2025 and all aspects of the project will be completed in 2026; this coincides with Engineering's Children's Bridge RMR that will be delivered under the same contract.

90% drawings were used to inform on the estimated costs for the budget request (Attachments: 90% Design: Power ...