recommendation

 

That 2027 funding for Capital Charter ENGS-058 (neighbourhood traffic calming) be reduced by $117,500.

 

body

Administration’s Understanding of the Intent of the Motion:

 

Administration understands that if passed, this motion shall reduce the requested funding within Charter ENGS-058: Neighbourhood Traffic Calming by $117,500.

 

SUMMARY

 

Council has an approved Traffic Calming Policy (C-TS-02) directing Administration to address resident traffic safety concerns at the neighbourhood level. Consistent with the policy, Administration is currently delivering a traffic calming program in the community of Riverside.

 

The proposed 2027 Traffic Calming program expands upon the work completed in 2026 that involved resident engagement, plan development, and temporary measure implementation; and the next year’s program and associated funding empowers completion of assessments of temporary measures, final resident engagement, and detailed design and construction of permanent measures.

 

Recognizing funding that is anticipated to be carried forward from the approved 2026 budget, Administration believes a reduction of $117,500 from the 2027 funding request can be accommodated while still enabling the planned completion of the Riverside Traffic Calming program.

 

ALIGNMENT TO COUNCIL DIRECTION OR MANDATORY STATUTORY PROVISION

 

On April 4, 2016, Council passed the following motions:

 

C185-2016

1.                     That Council Policy C-TS-02 Neighbourhood Traffic Calming, provided as Attachment 1, to the April 4, 2016, Agenda Report entitled “Proposed Council Policy C-TS-02 Neighbourhood Traffic Calming” be approved.

2.                     That the Neighbourhood Traffic Calming Process and Guidelines, provided as Attachment 2, to the April 4, 2016, Agenda Report entitled “Proposed Council Policy C-TS-02 Neighbourhood Traffic Calming” be received as information.

3.                     That Administration move forward with a pilot of the Neighbourhood Traffic Calming Process within the community of Erin Ridge, starting in Q2 of 2016.

 

BACKGROUND AND DISCUSSION

 

With the requested funding in Charter ENGS-058 Neighbourhood Traffic Calming, Administration is planning on completing the permanent construction of measures in the Riverside neighbourhood. This includes the additional scope associated with final temporary measure acquisition, installation, and assessment; further resident engagement to develop a final Traffic Calming Plan; and the engineering, detailed design, and construction/construction management service to implement the permanent works.

 

The 2027 program has applied estimates of construction from the developed plan and has also incorporated a value of potential grant funding, which would be used to offset a portion of the requested funding.

 

Based on the approved 2026 Traffic Calming budget and an updated assessment of direct program needs, Administration has identified approximately $117,500 that could be reduced from the 2027 funding request under Charter ENGS-058 Neighbourhood Traffic Calming for Council's consideration.

 

Maintaining all existing approved funds would best position Administration to respond to the next priority areas.  Approval of this motion, without approval of the full 2026 approved funds as carry forward, would reduce scope of Traffic Calming in the Riverside Neighbourhood. Reduction of the 2027 proposed budget could impact further new Traffic Calming in subsequent priority areas (Jensen Lakes, Lacombe Drive, Ebony Way).  Administration does not believe this reduction would place the grant funding at any risk, as the remaining value of funds maintains a required portioned share of funding from the City.

 

STAKEHOLDER COMMUNICATIONS OR ENGAGEMENT

 

The proposed Traffic Calming Program in 2027/2028 largely targets the continued work of delivering Traffic Calming improvements within the community of Riverside to which there has been multiple actions of resident engagement to first confirm community support of applying Traffic Calming to the community, identify issues and locations that were used to develop a concept plan for measures to be applied. Engagement has included:

 

1)                     2023 / 2024 - Residents applied to the Transportation group for Traffic Calming to be applied.

2)                     Fall 2024 - Community Support Survey to confirm support for Traffic Calming to be applied. 82% of respondents desired / supported Traffic Calming advancing.

3)                     Spring 2025 - Workshop conducted for issues and locations identification.

4)                     Fall 2025 - Survey of concept plan developed

 

Applicable temporary measures will be installed in Fall 2026 and Spring 2027, and further resident engagement will occur to seek feedback on the measures to inform on a potential final Traffic Calming Plan (planned engagement Fall 2027).

 

IMPACTS OF RECOMMENDATION(S)

 

Financial:

If approved, this motion will reduce the requested 2027 Traffic Calming budget by $117,500. Administration does not believe this reduction would put the grant funding at any risk, as the remaining value of funds maintains a required portioned share of funding from the City.

 

Compliance & Legal:

None at this time.

 

Program or Service: 

Without approval of the anticipated full funds for carry forward from the 2026 Traffic Calming; Neighborhood Traffic Calming would be potentially reduced in scope in Riverside, as well as possible downstream impacts to other neighbourhoods. 

 

Organizational:

None at this time.

 

Risks

None at this time.

 

ALIGNMENT TO PRIORITIES IN COUNCIL’S STRATEGIC PLAN

 

Initiative aligned with Strategic Plan:

Not Applicable

 

ALIGNMENT TO LEVELS OF SERVICE DELIVERY

Not Applicable

 

body

Report Date: November 24, 2026

Author(s): Dean Schick, Transportation Manager

Department: Engineering

Department Director: Dawny George

Managing Director:  Adryan Slaght

Chief Administrative Officer: William Fletcher