TAMRMS#: B05
6.13
title
Landscape Technician II Position
Notice given by: Councillor Hughes
label
BUDGET POSTPONED MOTION:
recommendation
That the Landscape Technician II Position for $98,700 is unfunded.
body
Administration’s Understanding of the Intent of the Motion:
That the Operating Business case for Landscape Technician II position be unfunded and $98,700 be transferred to the Growth Stabilization Reserve.
SUMMARY
Development landscaping review, approval, onsite construction reviews, inspection services, security reviews, project close out, and asset transfer are currently supported by two specialized resources.
Current resources are operating at or above capacity and relying on overtime to maintain service levels, creating risks to review timelines, staff sustainability, and service continuity. Anticipated growth with expansion areas to the west and northeast will further increase demand for these resources and the development team, widening the gap between available capacity and service requirements.
With the approval of the proposed motion, maintaining the current level of service will not be sustainable with available resources.
ALIGNMENT TO COUNCIL DIRECTION OR MANDATORY STATUTORY PROVISION
N/A
BACKGROUND AND DISCUSSION
Development landscaping review, approval, and inspection services are currently delivered by one Landscape Technician II, supported by one Landscape Technician I. The Landscape Technician II is responsible for the more complex technical reviews, inspections, warranty assessments, standards compliance, and project closeout activities associated with development projects.
There are currently 389 active Development Permit (DP) and Developer Agreement (DA) files requiring varying levels of review and inspection. On average, the total annual resource capacity requirement for landscaping review, inspection, asset acceptance, and administration of existing agreements is summarized below. With an average annual workload of 14 new DAs and 24 new DPs, combined with ongoing inspections, warranty reviews, and administration of existing agreements, development-related landscape reviews require approximately 2,428 field review hours annually.
Capacity Analysis summary of May through October for onsite inspection only:
|
Item |
Average Annual Volume (No. Of projects) |
Average Hours per project |
Average Annual Total hours |
|
New Development Agreement (DA) |
14 |
88 |
1,232 |
|
Ongoing DA warranty review and asset acceptance |
14 |
10 |
140 |
|
New Development Permits (DP) |
24 |
44 |
1,056 |
|
Total Annual Review Requirement |
n/a |
n/a |
2,428 |
During the primary construction season (May through October), available inspection capacity is approximately 900 hours per employee, resulting in an extrapolated requirement of 2.7 full-time staff. The above chart does not include drawing reviews, security release assessments, project closeout documentation, engineering standards updates, capital asset transfers, administrative reporting, and stakeholder coordination.
Current staffing resources are insufficient to meet existing service demands and maintain the established review timelines of 4-6 weeks for development drawing submissions. Existing staff are operating at or above full capacity and are relying on overtime to complete required reviews and inspections within the short construction season. The specialized technical knowledge required for landscape review and inspection limits opportunities for cross-training from other operational areas, creating a significant service delivery vulnerability should staff capacity be reduced through vacancies, absences, or turnover.
Future growth pressures will further increase workload demands. Major development areas including the Lakeview Business District, west area expansion, and northeast growth areas are expected to generate additional DAs, DPs, landscape inspections, warranty reviews, and compliance monitoring activities.
STAKEHOLDER COMMUNICATIONS OR ENGAGEMENT
Not applicable.
IMPACTS OF RECOMMENDATION(S)
Financial:
If the motion passes, $98,700 in unused assessment growth will be transferred to the Growth Stabilization Reserve in accordance with section ii. of Council Policy C-FS-05 Budget and Taxation Guiding Principles 14(b):
ii. Any portion of the 45 per cent of growth revenue not applied to business cases or capital charters during the budget process shall be transferred to the Growth Stabilization Reserve.
Compliance & Legal:
None at this time.
Program or Service:
If the motion passes, development review timelines will continue to increase beyond the service level established, impacting developer timelines and customer service expectations. Additionally, reduced inspection capacity may result in landscaping installations that do not meet Municipal Engineering Standards or approved development requirements.
Organizational:
Continuing to rely on existing staff to maintain service levels with the increased volume of work in the development area increases the risk of overtime, eventual loss of productivity resulting in staff burnout and reduced morale. Staff may also be susceptible to errors and omissions to meet the demand placed on them by the development community. Ultimately, to maintain the resource's health and safety, service levels would have to be adjusted which may not be well received by the development community who are used to the standard set in the previous years.
In addition, there is a potential for reduced resiliency within the development review team by increased dependence on a small, specialized resource to complete the tasks. Projected growth within west and northeast development areas will further widen the gap between workload demands and available staffing resources, increasing service delivery risks over time.
Risks
The following risks are anticipated if the motion passes.
People: Potential concern on specialized skill-person dependency, workload capacity, and retention of staff.
Stakeholders: Potential impact on relationships with the development community and the City’s reputation with reduced service levels
Asset Management -With the reduced capacity to meet demands, deficiencies may not be identified within warranty periods, increasing future maintenance costs and replacement liabilities. Oversight of invasive species management, tree protection, and landscape quality standards may be compromised.
ALIGNMENT TO PRIORITIES IN COUNCIL’S STRATEGIC PLAN
Initiative aligned with Strategic Plan:
None at this time
ALIGNMENT TO LEVELS OF SERVICE DELIVERY
C.1.3 Vegetation and Pest Control: Maintenance of healthy turf and urban forests
D.1.2 Issuance of Land Use and Development Permits and Licenses_ D.1.2.g Technical Drawing Reviews: Drawing evaluation is done within 4-6 weeks. Response times may vary due to the complexity of the request or the volume of requests.
body
Report Date: November 24, 2026
Author(s): Johnathan Reid
Department: Engineering
Department Director: Dawny George
Managing Director: Adryan Slaght
Chief Administrative Officer: William Fletcher