TAMRMS#: B05
5.8
title
RECR-050, RWP Meadowview Construction - Postpone
Notice given by: Councillor Hughes
label
BUDGET POSTPONED MOTION:
recommendation
That RECR-050 RWP Meadowview Construction is postponed for consideration to the 2028 budget.
body
Administration’s Understanding of the Intent of the Motion:
RECR-050 RWP Meadowview Construction charter will be unfunded from the 2027 recommended list and moved for consideration as part of the 2028 budget process.
SUMMARY
This report provides background on the charter strategy for completing the Red Willow Park West Master Plan and discusses impacts related to the above postponed motion.
ALIGNMENT TO COUNCIL DIRECTION OR MANDATORY STATUTORY PROVISION
None at this time.
BACKGROUND AND DISCUSSION
In alignment with the Red Willow Park West Master Plan, capital work was split into three phases:

The scope of work proposed for Phase 3 reflects the work required to complete the vision and intent of the Red Willow Park West Master Plan and, more specifically, the role of White Spruce Park as an educational destination and key access point to both the existing Red Willow trail system and planned expansions into Lakeview Business District.
Delaying this work will extend the provision of a lower level of service to the community and limit the capacity for the park and trail system to meet its intended program. Reflecting general construction trends, it is anticipated that cost to construct will also increase.
The proposed delay of washroom facilities and parking infrastructure may not align with established Parks and Open Space Standards or the level of service typically required by park users. Further, the delay of interpretive signage may limit educational opportunities potentially reducing visitor engagement and the overall effectiveness of the park as a recreational and learning destination.
STAKEHOLDER COMMUNICATIONS OR ENGAGEMENT
Engagement on the Red Willow Park West Master Plan and design for all three phases of construction were completed in 2018 and 2020, respectively.
Work with interested community stakeholders and Indigenous partners on interpretive themes and options for interpretation occurred across 2025 and 2026. This work was done in coordination with public engagement for a public art installation that has been funded for inclusion within the overall project area.
IMPACTS OF RECOMMENDATION(S)
Financial:
If approved, this motion will unfund the RECR-050 RWP Meadowview Construction project along with any operating impacts, therefore increasing the amount of capital dollars available for future prioritized capital projects as well as emergent capital items.
Compliance & Legal:
None at this time.
Program or Service:
The course of action outlined in the proposed motion is likely to result in an extended reduction in user experience, as reflected by inquires/complaints related to the site.
Parking will continue to be provided through on-street parking in adjacent neighbourhoods if this project is not completed.
Organizational:
None at this time.
Risks
The City could face a reputational risk related to engagement work with Indigenous partners and community stakeholders related to delays in delivery of the interpretive program. The change in project scope would need to be communicated accordingly.
Costs for delivery of the full capital program are likely to increase through a delay in delivery, as extended timelines may result in construction cost escalation, increased consultant and administration fees, and reduced purchasing certainty.
ALIGNMENT TO PRIORITIES IN COUNCIL’S STRATEGIC PLAN
Initiative aligned with Strategic Plan:
None at this time
ALIGNMENT TO LEVELS OF SERVICE DELIVERY
A. Community Amenities
1. 4 Parks, Open Spaces and Recreation Sites - Ensure the provision of recreation and park sites for community users in a safe and comfortable environment.
1. 5 Recreation and Sport Amenities - Ensure the provision of scheduled and spontaneous use of recreation amenities for community users in a safe and comfortable environment
D. Land Use and Development
3.3.a Parks Planning and Development - The process of using identified and demonstrated community need to plan and construct new and redeveloped park sites and amenities that reflect a wide variety of recreation, school, community services and conservation priorities.
body
Report Date: November 24, 2026
Author(s): Craig Cameron, Manager, Parks and Community Partnerships
Department: Recreation and Parks
Department Director: Daniele Podlubny
Managing Director: Dinu Alex
Chief Administrative Officer: William Fletcher